Engineers and Consultants to the Oil and Gas Industry

The Oil & Gas Division of Sir Fredrick Snow & Partners Ltd.

8th Floor Corinthian House

                        17 Lansdowne Road

         Croydon

CR0 2BX

Phone: +44  20 86048999
Fax: +44 20 86048877

 

________________________________________________________________________________________________

 

Below is a partial listing of out past projects:

(Click the project name to view a brief summary)

 

                                                                                                                                                                                   

 

 

 

 

________________________________________________________________________________________________

 

·  

CLIENT / PROJECT HISTORY — Transco (British Gas). In 1998 Transco awarded IMEG a contract to carry out a conceptual study of the addition of gas cooling and estimate the capital and operating costs.

PROJECT DESCRIPTION — Long term forecasts predict an increase in flow through the Huntingdon Compressor Station to 85 Mscmd. By reducing the discharge temperature form Huntingdon the overall network capacity can be increased.

IMEG’s RESPONSIBILITY — The IMEG study addresses the implications of installing a cooler at the discharge of the Huntingdon Compressor Station to reduce the temperature to +30ºC. It also provides an estimate for the total cost to implement the proposals.

________________________________________________________________________________________________

 

·  

CLIENT / PROJECT HISTORY — Transco (British Gas). In late 1997 IMEG were commissioned to undertake a Conceptual Engineering Study to review the additional compression required to increase the gas supply to Ireland, together with the cost and implications of installation in their existing Compressor Station in Moffat, Scotland.

PROJECT DESCRIPTION — The study was for the construction of additional compression facilities within the existing Moffat Compressor Station to satisfy the increasing Irish gas demand. The preferred solution was three turbo-compressor units, two (1+1) 13-15 MW units and one 8 MW unit.

IMEG’s RESPONSIBILTY — Following discussions between IMEG and Transco BG, IMEG were commissioned to perform a study on the implications of installing additional compression at Moffat Compressor Station.

________________________________________________________________________________________________

 

·  

CLIENT / PROJECT HISTORY — CNO (Constructora Norberto Odebrecht). IMEG was awarded a contract in 1997 by CNO to carry out certain engineering services in respect of their tender for the Mega Condensate Pipeline in Argentina.

PROJECT DESCRIPTION — 600km of 12” dia NGL pipeline and 2 pumping stations.

IMEG’s RESPONSIBILITY — Three technical reports prepared by IMEG during 1997 for CNO:

* Hydraulic Study

* Alternative Hydraulic Study

* Material Take off

________________________________________________________________________________________________

 

·  

CLIENT / PROJECT HISTORY — Investors in Partnership with Occidental. In 1996 IMEG were asked to undertake a site visit to the Usinskoye Field in the Komi Republic and to investigate the technical and economical viability of the Field from an investment viewpoint.

PROJECT DESCRIPTION — The Unsinskoye Oil Field is operated by Nobel Oil and produces sour and exceptionally heavy crude oil. In order to increase production s steam flood scheme has been installed consisting of 8 permanent steam generators to ‘flood’ the field and 2 mobile steam generators to ’Huff Puff’ single production wells. This brief study is to assess the success of the system and to comment on the future investment.

IMEG’s RESPONSIBILITY — Visit site, make a general overview of the Field and assess current technology, operation, procedures and management. Prepare a Report with all findings and comment on future investment potential.

________________________________________________________________________________________________

 

·  

CLIENT / PROJECT HISTORY — Occidental / Parmaneft. In 1996 IMEG were commissioned to undertake an Appraisal Study for development of a number of oil fields in Block 15 of the Komi Republic of Russia.

PROJECT DESCRIPTION — Five separate fields have been identified in ’Block 15’. This study deals with the first two fields to be developed, North Kozhvinskoe and South Lyzhskoe together with an export pipeline and a terminal with injection into the main trunkline. These fields have a high wax content in Artic conditions.

IMEG’S RESPONSIBILITY — Review and appraise previous proposals and recommend optimum system for production, gas treatment, water injection, pumping, pipeline and terminal facilities, with a view to minimising capital investment. 

________________________________________________________________________________________________

 

·  

CLIENT / PROJECT HISTORY — Cooper Energy Services. In 1994 IMEG carried out a Process Design Review for Cooper Energy Services UK of the major process elements of the Kupal Gas Compressor Station in Iran.

PROJECT DESCRIPTION — The principle objective of this review was to determine if the basic design satisfies the specified operating conditions whilst being capable of providing reliable and safe operation at other conditions within the limits of the compression equipment and the station control system. The design comprised of 2+1 Avon Compressors (45,000 installed HP) Pressure 27– bar g. Flow 150 M MSCFD.

IMEG’S RESPONSIBILTY — IMEG’s brief extended to examining features of the design that might prevent satisfactory operation of the station under specific conditions and to making recommendations for corrective changes in the design.

________________________________________________________________________________________________

 

·  

CLIENT / PROJECT HISTORY — NADYMEG (for Komsomolsk-Na-Amure Oil Refinery). The refinery at Komsomolsk has a capacity of 6 m.t.a. but is in need of upgrading and rehabilitation. It obtains crude for Okha, Sakhalin Island, by pipeline 650km to the north.

PROJECT DESCRIPTION — A review of two alternative routes for exporting 2.8 m.t.a. of refined products from the Komsomolsk Refinery. The products proposed for export are diesel, gasoline and kerosene. The alternatives are either to follow the existing crude oil line from Sakhalin and construct a new jetty and terminal at De Kastri, or adopt a new pipeline route to Vanino and construct a new storage terminal, but use the existing jetty.

IMEG’s RESPONSIBILTY — A technical report was prepared in 1995 on the concept that a 324km multi-products pipeline to DE Kastri with four pump stations including one to Kosomolsk, a tank farm and loading terminal is the  more economic solution.

________________________________________________________________________________________________

 

·  

CLIENT / PROJECT HISTORY — NADYMEG (for GAZPROM). The Yamal Peninsular in north western Siberia contains vast reserves of natural gas. Figures in excess of 10 Trillion Cubic Metres of proven reserves have been cited with the likelihood  of probable reserves being well in excess of this. The Russian gas company Gazprom has developed plans for exploiting this huge resource by building a pipeline transmission system to carry the gas to markets in Europe. This development will be a massive undertaking which will provide a significant proportion of Russian and European energy requirements well into the next century.

PROJECT DESCRIPTION — Initial Section of Yamal Peninsular to Europe Pipeline:

* Period 1995

* Design throughput of 9285 M MSCFD

* 90km of 3 x 56” diameter gas pipeline

IMEG’s RESPONSIBILITY — Personnel form IMEG examined the terrain and assessed the difficulties that will be encountered un constructing  this section of the pipeline. A Pre-investment Economic and Technical Study of the project was prepared.

________________________________________________________________________________________________

 

·  

CLIENT / PROJECT HISTORY — NADYMEG (for Sakhalinmorneftegaz). In 1995 IMEG were commissioned to undertake a Technical and Economic Appraisal for the rehabilitation of an existing corroded pipeline and the increase in the capacity for the future offshore crude production.

PROJECT DESCRIPTION — Replace the entire old pipeline form km 165 to km 616 (Komsomolsk) with the exception of the Amure river crossing and the sea crossing at Lazarevo. Initiate, survey, design and build offloading facilities at De Kastri to handle the importation of 3 to 3.5 m.t.a. of crude. The installation of modern leak detection facilities including a computer automation system and reliable telecommunications.

IMEG’s RESPONSIBILTY — The report covers the technical and pre-investment aspects of the reconstruction of the Okha / Komsomolsk—Na-Amure crude oil pipeline. The technical parameters are defined and basic engineering concepts are proposed. A capital cost estimate based on International norms is included and transportation of oil rates are considered.

________________________________________________________________________________________________

 

·  

CLIENT / PROJECT HISTORY — Tyumenneftegaz. In 1994 IMEG were instructed to carry out Pre-investment Technical and Economical Appraisal for the development of Tailakovskoye, Polynyakhskoye and adjacent oil fields, together with proposals for an export pipeline. IMEG together with reservoir specialist Wavetech visited the area to collect all available data

PROJECT DESCRIPTION — From available date the option plan was to undertake development drilling on a fairly large scale in both the two main fields and adjacent fields. This could lead to extraction of 101m tones of oil 5 BCM of gas over a 43 year period. The recommended configuration was for a treatment plant, 275km of 16” dia transmission pipelines and 1 intermediate pump station

IMEG’s RESPONSIBILITY — To gather all available local data and to undertake a Field Development Study.

________________________________________________________________________________________________

 

·  

CLIENT / PROJECT HISTORY — The Government of Turkmenistan. In 1994 IMEG undertook a study for TOGET (Turkmenistan Oil and Gas Export Trunklines Limited), and prepared a report “Concept and Approach” for development of gas fields in Western Turkmenistan together with a proposal for a large diameter pipeline to transport the gas via Iran to Turkey.

PROJECT DESCRIPTION — Development of up to 13 gas fields in Western Turkmenistan, gas gathering pipelines, gas treatment, 56” diameter pipeline to Iranian border, 1260km of 56” diameter pipeline through Iran and across the Iran — Turkey border, 8 compressor stations and 3 custody metering stations

IMEG’s RESPONSIBILTY — To provide consultancy services. To study the existing fields and assess their potential for development. Undertake conceptual design and purpose pipeline routing, number compressor and metering stations, estimate all plant and construction costs. Produce a report for the Government of Turkmenistan.

________________________________________________________________________________________________

 

·  

CLIENT / PROJECT HISTORY — Cooper Rolls (for National Iranian Oil Company). In 1994 IMEG were commissioned to perform an engineering review of the original design and identify the affect on major equipment and of the process implications of using 3+1 compressors instead of 4+1.

PROJECT DESCRIPTION — The Parsi Gas Injection Project was engineered by Sazeh Consultants for the National Iranian Oil Company Southern Fields. This project included a compressor station with four operating turbo-compressor  units plus a standby unit. Cooper-Rolls were invited to bid for the supply of turbo-compressors. Cooper-Rolls identified an alternative solution using only three working units plus a standby unit, which offered significant capital cost savings, but with the implication of an impact to the overall station design.

IMEG’s RESPONSIBILTY —  The Scope of work covered by the commission were consultancy services and design audit. Work commenced on 18th May 1994 and was completed on the 15th June 1994. the scope was enlarged by a request to justify the selection of the three plus one solution.

________________________________________________________________________________________________

 

·  

CLIENT — Occidental of Oman Inc.

PROJECT DESCRIPTION —  Safah Gas Compression Facilities Project:

* Period 1992-1994

* Value $32 million

* Design throughput of 50 M MSCFD

* Discharge pressure 4,500 psig.

* 1 x 12,600 hp Gas Turbine Driving 2 Centrifugal Compressors giving injection pressure of 310 bar g

IMEG’s RESPONSIBILTY — Lump Sum Turnkey Contractor

________________________________________________________________________________________________

 

·  

CLIENT — Nigerian National Petroleum Corporation (NNPC)

PROJECT DESCRIPTION — Escravos—Lagos Gas Pipeline System:

* Warri and the swamplands to the West

* Period 1987—1993

* Value $300 million

* 4 x Compressor Stations—15,200 installed hp

* Gathering System—100km of 8” to 24” diameter Pipeline

* Warri Gas Treatment Plant 300 MMSCFD

IMEG’s RESPONSIBILTY —  

* Cathodic Protection, Topographic and Soil Surveys and Gas Analysis

* Detailed Engineering Design

* Procurement of Cathodic Protection Material

* Field Engineering

* Commissioning

________________________________________________________________________________________________

 

·  

CLIENT / PROJECT HISTORY — Shell UK Exploration and Production. 1991—Project commencement following UK Government Department of Energy requirement that detailed drawings and m.t.o.’s be submitted with applications for Work Authorisations.

PROJECT DESCRIPTION — Itemising of North Sea oil production fields Gannet ‘C’ subsea wellhead and collection system pipework and production platform Gannet ‘A’ topsides pipework.

IMEG’s RESPONSIBILITY — Detailed draughting of isometric drawings and creation of database of pipe and pipe fittings relating to subsea towheads, pipe bundles and production platform risers and topsides pipework.

________________________________________________________________________________________________

 

· Gas Utilisation Project — Malaysia

CLIENT — Petronas Gas SND. BHD.

PROJECT DESCRIPTION — Peninsular Gas Utilisation Project—Stage II

* Period 1988-1991

* Value $350 million

* 705km Pipeline of 30” and 36” diameter

* 1000 MMSCFD Total Gas Flow

IMEG’s RESPONSIBILTY —  (In association with MMC Engineering Services)

* Project Management

* Environmental Study

* Detailed Design and Engineering

* Line Pipe Inspection

* Environmental Audit System Development and Monitoring

* Field Engineering Assistance

* Commissioning Assistance

________________________________________________________________________________________________

 

Addition of Gas Cooling at Huntingdon Compressor Station - United Kingdom

Huntingdon Compressor Station

Moffat Compressor Station - United Kingdom

Moffat Compressor Station

Mega Condensate Project - Argentina

Mega Condensate Project

Usinskoye Oil Field Development - Russia

Usinskoye Oil Field

Block 15 Field Development - Russia

Block 15 Field

Kupal Gas Injection Compressor Station - Iran

Kupal Compressor Station

Komsomolsk Oil Refinery Products Pipeline - Eastern Siberia

Komsomolsk Pipeline

Yamal to Europe Gas Pipeline System - Russia

Yamal to Europe Pipeline

Sakhalin Island to Komsomolsk Crude Oil Pipeline System - Eastern Siberia

Sakhalin Island to Komsomolsk Pipeline

Tyumen Region Field Development - Russia

Tyumen Region Field

Gas Pipeline - Turkmenistan to Turkey

Turkmenistan to Turkey Pipeline

Parsi Gas Injection Compressor Station - Iran

Parsi Compressor Station

Safah Field Gas Injection Project - Oman

Safah Field Project

Gas Gathering System - Nigeria

Nigeria Gas Gathering System

North Sea Gannet C Field - United Kingdom

North Sea Gannet C Field & Malaysia Gas Utilisation Project

Projects

IMEG’s four most recent projects can be viewed in further detail by clicking on the pictures below


Aberdeen Feeder 13


Bathgate Compressor Station

Moffat Compressor Station

Compressor Station Feasibility Studies

 

Home

 

About IMEG

         

 

Services

 

 

Clients

 

Computer Facilities

 

Contact